The short answer: In many commercial leases, rent doesn’t start the day you sign. The lease sets a separate rent commencement date, and the way that date is defined decides whether you pay rent while your space is still under construction. Common triggers are a fixed calendar date, completion of the landlord’s work, or the earlier of your opening day or a set number of days after delivery. Which one you get is negotiated, so the time to sort it out is before you sign.

Here’s a situation that plays out more often than it should. A business owner negotiates “four months of free rent for the build-out” and signs. The landlord takes weeks to approve the plans, plan check comes back with corrections, and the electrical gear has a long lead time. The free months run out, and rent is due on a space that can’t open yet.

Nobody broke the lease. Rent was tied to the calendar, while the build-out was tied to approvals and deliveries. Below: how rent start dates work, what delays a build-out, what happens when permits or the landlord run late, and what to settle before you sign.

“Do I pay rent while my space is under construction?”

It depends entirely on your lease. A commercial lease often has several different dates, and people mix them up:

TermWhat it usually means
Lease executionThe day both sides sign
Delivery or possession dateThe day you get the keys and can start work
Lease commencement dateThe day the lease term (for example, five years) starts counting
Rent commencement dateThe day you start paying rent
Free rent or abatement periodA stretch where some or all rent is waived, often meant to cover the build-out
Outside dateA deadline in the lease; missing it can trigger a remedy, such as extra free rent or a right to terminate

Lease commencement and rent commencement are not always the same day. The gap between them is where your build-out time lives.

One detail to check: “free rent” doesn’t always mean free. Some leases waive base rent but still charge your share of operating expenses, such as taxes, insurance, and common area costs. Ask exactly which charges are waived.

What are the common ways a lease sets the rent start date?

There’s no standard formula. These are the patterns you’ll see most often:

How rent start is setHow it worksWho mostly carries the delay riskWhat to watch
Fixed dateRent starts on a calendar date, finished or notYouBuild in a realistic cushion
Set number of days after signingThe clock starts at signing, before design or permitsYouDesign and plan check eat into the free time
Completion of the landlord’s workRent starts when the landlord’s work is substantially completeMostly the landlordHow “substantial completion” is defined
Earlier of opening or a set number of days after deliveryRent starts when you open, or at a backstop date, whichever comes firstSharedWhat “delivery” means and when it really happens
Set number of days after the latest of possession, plan approval, and your permitThe backstop clock waits for key approvalsMore evenly sharedEach trigger needs a clear definition

That last option is worth knowing about. A sample retail lease presented at a 2021 ICSC legal conference set the backstop at 120 days after the latest of possession, plan approval, and the tenant’s building permit. That’s one example, not a typical number.

A useful rule of thumb from Los Angeles real estate attorney Sandra Gold Slon of TroyGould: “the party who controls the construction is the party who assumes the risk of a delay in completion.” Run your own build-out and the landlord will likely want a fixed date; if the landlord builds, rent more often waits for completion. Our guide to landlord build vs. tenant build walks through how that choice shifts cost, control, and schedule risk.

What actually slows a build-out down?

Usually not the construction itself. On many tenant improvements, the slow parts come before and around the work:

For a phase-by-phase look, see how long a commercial tenant improvement takes. The short version: size your rent-free period to the whole process, not just the weeks a crew is on site.

Does a permit delay push back my rent start date?

Only if your lease says so. Permit timing is one of the most negotiated points in this whole topic.

A 2023 article on lease work letters in the American Bar Association’s Probate & Property magazine describes the landlord’s usual position when the tenant does the work: rent shouldn’t depend on the tenant finishing, and the date is typically set a number of days after signing, extended only for delays the landlord actually caused. Whether force majeure covers “delays in permitting” is, in the authors’ words, “a matter of negotiation between the parties.”

The flip side: when you’re waiting on the landlord’s work, a June 2026 Holland & Knight article notes that tenants may want to exclude “routine permitting issues, supply chain problems and contractor underperformance” from the landlord’s excuses. If you’re building, you want permit delays to move your rent date. If the landlord is building, you may not want routine permit delays to excuse a late delivery.

What happens if the landlord’s work is late?

If the landlord has to finish work before you can build or open, the lease should say what happens when it runs late. Common tools include a day-for-day extension of your rent start date, extra free rent after a grace period, an outside date with a right to terminate, and self-help rights to finish the work yourself and offset the cost.

The Holland & Knight article makes a point worth remembering: “rent tolling alone rarely solves the business problem created by a delayed delivery.” A later rent date helps, but it doesn’t cover a missed season, staff you already hired, or rent at your old location.

Also look closely at how “substantial completion” is defined, because that’s often when rent starts. Slon recommends that the definition include a certificate of occupancy. Many tenants also ask for early access so phone, data, and fixture installers can start before the official completion date.

What counts as “tenant delay,” and why should you care?

Many leases let the landlord move your rent date earlier, day for day, when you cause a delay. That’s fair in principle. The trouble is vague wording: a phrase like “lack of timely response” can turn a slow email into a rent-date change. Slon suggests defining tenant delay as failing to respond “within a specified number of days from request.” Asking for prompt written notice of any claimed tenant delay also helps, so you can fix it right away.

Questions to settle before you sign

Use this as a conversation list with your broker, attorney, and contractor:

What can I figure out myself, and when should I bring in help?

You can usually handle: pulling every date out of the letter of intent or draft lease, putting them on one calendar, and asking which event starts rent and which charges are waived.

Bring in a contractor when: you need a realistic schedule for design, permits, long-lead items, and construction before you agree to a free-rent period.

Bring in your attorney and broker when: you’re negotiating rent start language, force majeure, tenant delay, and remedies. Attorneys writing about retail leases note that courts generally enforce clear rent terms as written, so fix the wording before you sign. This article is general information, not legal advice.

Frequently asked questions

What is a rent commencement date? It’s the day you start paying rent under a commercial lease. It can be different from the day you sign or the day the lease term begins, and the lease decides what triggers it.

What is the difference between lease commencement and rent commencement? Lease commencement is when the lease term starts counting. Rent commencement is when payments begin. The time between them is often used for the build-out.

Do I have to pay rent during a build-out? It depends on your lease. Many tenants negotiate a free rent period or a rent start date tied to completion or opening, but some leases start rent on a fixed date whether the space is finished or not.

Does a permit delay extend my free rent period? Only if the lease says it does. Whether permit delays extend the rent start date is a negotiated point, so ask for it in writing before you sign.

How long should a free rent period for a build-out be? Long enough to cover design, landlord approval, plan check, construction, and final sign-offs, plus a cushion. That varies widely by project type and city, so get a project-specific schedule before you agree to a number.

Signing soon? Get a real schedule before the rent clock starts

A free rent period is only as good as the schedule behind it. Before you agree to a number, know what your space will actually take: design, city review, long-lead equipment, and the cost of the work line by line.

De Sisto Construction, Inc. is a California licensed general contractor (CSLB #803545) based in Signal Hill and serving greater Los Angeles and Orange County since 2001. Our commercial work includes tenant improvements, build-outs, offices, retail, and restaurants, and we guide permitting, inspections, and code-compliance coordination with step-by-step outlines and line-item project costing. Learn more about our commercial build-out services for businesses.

Give us a call at 562-425-1050 or email us at info@desistogc.com (dcidirect.net)

Leave a Reply

Your email address will not be published. Required fields are marked *