The short answer

A mechanics lien is a legal claim against your property, recorded by someone who worked on it or supplied materials and says they were not paid. In California, a subcontractor or supplier can record one even if you paid your contractor in full, which is how homeowners end up paying twice. You protect yourself by tracking preliminary notices, collecting lien releases with every payment, and knowing the deadlines that make a lien expire.

“Can a subcontractor put a lien on my house even though I paid my contractor?” It is one of the most common questions California homeowners ask, usually after an envelope arrives in the middle of a remodel from a company they have never heard of. The honest answer is yes, they may be able to. The good news is that the law also gives you warning signs, paperwork, and deadlines that work in your favor, if you know where to look.

Here is how the system works, what that envelope actually means, and what to do if a lien ever lands on your title.

What is a mechanics lien, in plain English?

According to the Contractors State License Board (CSLB), a mechanics lien is a claim against, or security interest in, your property. If the debt goes unpaid, it can support a court action to sell the property to cover what is owed. It is recorded with the county recorder, so it shows up on your title.

Who can record one:

That second and third group is where homeowners get surprised. You never signed anything with the drywall supplier, but the law lets that supplier look to your property for payment if your contractor does not pay them. CSLB puts it plainly: if your contractor fails to pay subcontractors or suppliers, you may have to pay them yourself, in addition to what you already paid.

This is why every California home improvement contract must include a Mechanics Lien Warning. Our guide to what a California home remodeling contract should include covers that warning and the other required notices.

I got a “preliminary notice.” Is that a lien?

No. This is the most important thing to know, and it is where many homeowners panic for nothing.

A preliminary notice is a heads-up, not a claim. CSLB describes it as a notice that a subcontractor or supplier has provided, or will provide, labor or materials to your project and could record a lien if they are not paid. Under Civil Code Section 8204, it is generally due within 20 days after they first furnish work. If they send it late, they can usually only claim for work done within the 20 days before the notice and anything after.

Your own contractor and individual laborers generally do not have to send one. Subcontractors and suppliers do, if they want to protect their lien rights.

So when a preliminary notice arrives, treat it as a list of who to keep track of:

A stack of preliminary notices on a bigger project is normal. Suppliers send them routinely. The notice that should worry you is the one you never knew about, which is why keeping them organized matters.

How do I keep from paying twice?

Most of the protection happens during the job, not at the end. These are the habits CSLB recommends, in the order they come up.

WhenWhat to doWhy it helps
Before you hireVerify the contractor’s license and ask who their main subcontractors and suppliers will beTells you who could have lien rights
At contract signingMake sure the payment schedule ties each payment to completed workKeeps you from paying ahead of the work
During the jobKeep every preliminary notice you receiveYour list of potential lien claimants
Before each paymentGet a conditional lien release from each party being paid from that paymentIt takes effect only once they are actually paid
After each payment clearsGet the unconditional release, signed by the actual claimantConfirms they were paid
If releases are missingCSLB says you may withhold the next payment until you get unconditional releases for the previous oneKeeps the paperwork current
For larger amountsConsider a joint check made out to both the contractor and the sub or supplierCSLB calls it the simplest way to make sure they get paid
At the endConsider recording a Notice of CompletionShortens the time to record a lien

You can also ask for subcontractor details. Under a law that took effect January 1, 2026 (SB 517, as summarized by CSLB), if your contractor uses subcontractors, you can request each one’s name, contact information, license number, and classification.

The end-of-job steps (final releases, the four statutory release forms, and the Notice of Completion) are covered in detail in our post on when to make the final payment on a remodel.

What are the deadlines that matter?

Liens run on strict clocks. Missing one can make a lien unenforceable, which is why these dates are worth knowing.

DeadlineRule (California Civil Code and CSLB guidance)
Preliminary noticeGenerally within 20 days after the claimant first furnishes work (Section 8204)
Recording a lien, no Notice of CompletionGenerally within 90 days after completion of the work
Recording a lien, with a valid Notice of Completion60 days after recording for your direct contractor; 30 days for subcontractors and suppliers
Notice of CompletionRecorded by the owner within 15 days after completion
Enforcing a recorded lienThe claimant must file a court action within 90 days after recording, or the lien expires and is unenforceable (Section 8460), unless an extension of credit was properly recorded

Two more limits work in your favor. Under Civil Code Section 8430, a lien cannot exceed the lesser of the reasonable value of the claimant’s work or the price they agreed to. And according to CSLB, an unlicensed contractor cannot foreclose on a lien for work valued over $500.

What do I do if a lien is recorded on my house?

First, do not panic, and do not ignore it. A recorded lien stays on your title until it is removed, and CSLB notes it can block a sale, a refinance, or a line of credit.

CSLB’s guidance boils down to these steps:

  1. Check whether it may be invalid. A lien may not be valid if the work was not completed, the materials were not part of the project, a deadline was missed, or you were not properly served with the lien and its notice.
  2. Check whether a lawsuit was filed. If the claimant does not file an action within 90 days of recording, the lien expires. You can check with the local superior court.
  3. Ask for removal in writing. If the lien is invalid or expired, send the claimant a written request by certified, registered, or express mail explaining the problems, and keep copies and postal receipts.
  4. Go to court if needed. If the claimant will not remove an invalid lien, you can petition the court to release your property. CSLB describes this as complicated and recommends an attorney.

If the lien may be valid, talk with a construction attorney before you pay anyone, and gather your contract, payment records, preliminary notices, and any releases you collected. This article is general information, not legal advice.

When to handle it yourself vs. when to call a pro

You can handle: checking your contractor’s license, keeping a folder of preliminary notices, asking for releases with each payment, asking for the subcontractor list, and tracking your payment schedule against the work.

Get help when: a lien has been recorded, you cannot confirm that a subcontractor or supplier was paid, your contractor stops responding, you are deciding whether to record a Notice of Completion, or you are being asked to pay a party you have no contract with. A construction attorney or title company can help with the legal steps.

FAQ

Can a subcontractor put a lien on my house if I paid my contractor? Yes, they may be able to. CSLB warns that if your contractor does not pay subcontractors or suppliers, they can record a lien and you may have to pay them too. Lien releases and joint checks are your main protection.

Is a preliminary notice the same as a lien? No. It is a notice that a subcontractor or supplier is working on your project and could record a lien if not paid. Keep it and collect a release from that company when you pay.

How long does someone have to record a mechanics lien in California? Generally 90 days after the work is completed. If you record a valid Notice of Completion, that drops to 60 days for your direct contractor and 30 days for subcontractors and suppliers.

How long does a mechanics lien last? The claimant must file a court action within 90 days after recording it, or the lien expires and is unenforceable, unless an extension of credit was properly recorded.

How do I remove an invalid mechanics lien? Send the claimant a written removal request by certified mail explaining the problems. If they refuse, you can petition the court for a release. An attorney is strongly recommended.

Want fewer surprises on your next project?

Lien problems usually start with unclear payment schedules and missing paperwork. DCI is a California licensed general contractor (CSLB #803545) in business since 2001, and we build our projects around step-by-step outlines and line-item costing, so you can see what each payment covers. If you are planning a remodel, addition, or ADU, learn more about our residential construction services.

Give us a call at 562-425-1050 or email us at info@desistogc.com (dcidirect.net)

Leave a Reply

Your email address will not be published. Required fields are marked *