CA License #803545 

The short answer: Make the final payment when the work in your contract is done, the punch list is finished (or the open items are written down with dates), the city’s final inspection is signed off if the job had a permit, and you have the lien releases you need. In California, get a conditional lien release before you pay and an unconditional release after the payment clears. If you’re thinking about recording a Notice of Completion, plan ahead, because the deadline is only 15 days after completion.

The last payment on a remodel feels like it should be the easy one. The tile is grouted and you can finally use the room again. But it’s also when small loose ends turn into real headaches: a door that won’t close, an inspection nobody scheduled, or an unpaid supplier who can still record a lien on your home.

A clean finish is mostly about order. Here’s how to walk the job, what to have in hand before the last check, and what California law says about lien releases.

What is a punch list, and what isn’t on it?

A punch list is a written list of small items that still need fixing or finishing before the job is complete. Think touch-up paint, a missing outlet cover, a drawer that sticks, a caulk line that needs redoing, or a scratched fixture that needs to be replaced.

It’s not a place for new work. If you decide during the walkthrough that you’d like a different light fixture or an extra shelf, that’s a change, and it should go through a written, signed change order like any other change. Our guide to what a change order is and how to avoid surprise costs explains how those work in California.

How do I do the final walkthrough?

Schedule the walkthrough with your contractor once the work is substantially done and cleaned up. Bring the contract, plans, selections list, and change orders, and go room by room in daylight.

Write each item down with its location and a photo, agree on a date for each fix, and have both of you initial the list. A shared list is much easier to close than one that grows by text message.

What should be done before I make the final payment?

Before final paymentWhy it mattersHow to confirm
Contract work completeYou’re paying for finished workCompare the job to the contract scope and plans
Punch list done, or open items listed with datesSmall items are easy to lose track of once the money is paidA signed punch list with each item checked off
Change orders reconciledThe final number should match the contract plus signed changesA written final accounting: contract price, each change order, payments made, balance due
Final inspection approved (if the job had a permit)Permitted work isn’t approved until the inspector signs it offThe signed inspection card or the permit status online
Lien releases in handSubcontractors and suppliers can have lien rights even if you paid your contractorConditional release before you pay, unconditional release after it clears
Warranties, manuals, and product detailsYou’ll need them for future claims and careManufacturer paperwork, paint colors, model numbers
Cleanup and site restoredPart of finishing the jobWalk the yard, driveway, and work areas

On the inspection point: the Los Angeles Department of Building and Safety, for example, says permitted work is not approved until it has been inspected and accepted by its inspection staff, and that a completed project gets a final inspection and approval. Other cities run their own process, so check with yours.

What does California law say about paying as the work is done?

California’s home improvement contract law (Business and Professions Code section 7159) requires a schedule of progress payments tied to specific work. It also requires a notice in the contract that it is against the law for a contractor to collect payment for work not yet completed, or for materials not yet delivered. In practice, the final payment should line up with the final stage of work in your payment schedule, not with the day the last cabinet goes in.

Our guide to what a home remodeling contract should include in California walks through the required parts, including the payment schedule and the mechanics lien warning.

Why do lien releases matter at the end of a job?

Here’s the part that surprises many homeowners. The Contractors State License Board (CSLB) points out that paying your contractor, or getting a release from your contractor, does not guarantee that subcontractors and suppliers were paid. Those people may be able to record a mechanics lien on your property if they aren’t paid.

Lien releases close that gap. California uses four statutory forms, set out in Civil Code sections 8132 through 8138:

Release formWhen it’s used
Conditional Waiver and Release on Progress PaymentBefore a progress payment; it takes effect only once the claimant is actually paid
Unconditional Waiver and Release on Progress PaymentAfter a progress payment has been received
Conditional Waiver and Release on Final PaymentBefore the final payment; it takes effect only once the claimant is actually paid
Unconditional Waiver and Release on Final PaymentAfter the final payment has been received

CSLB’s guidance comes down to a few habits:

For releases, start with anyone who sent you a preliminary notice, and ask your contractor for a list of subcontractors and major suppliers.

What is a Notice of Completion, and should I record one?

A Notice of Completion is a document the owner can record with the county recorder after the work is complete. Under Civil Code section 8182, it has to be recorded within 15 days after the date of completion.

Why bother? It shortens the window for recording a lien. Without one, a direct contractor, subcontractor, or supplier generally has 90 days after completion. With a valid recorded notice, that becomes 60 days after recording for the direct contractor and 30 days for other claimants (Civil Code sections 8412 and 8414).

A few cautions before you record one:

Many owners have a title company or construction attorney help with this step. This article isn’t legal advice.

What if a few small items are still open?

If your contract includes retention (an amount held back from each payment until the end), Civil Code section 8812 says an owner who withholds it must pay it within 45 days after completion.

What can I handle myself, and when should I get help?

You can usually handle: the walkthrough and punch list, comparing the final invoice to the contract and change orders, checking permit status, collecting warranties, and asking for lien releases.

Get help when: you can’t confirm a subcontractor or supplier was paid, the contractor stops responding, you’re deciding whether to record a Notice of Completion, a lien has been recorded, or you disagree about what’s owed.

Frequently asked questions

Should I pay my contractor before the final inspection? If the job has a permit, it’s reasonable to tie the final payment to final inspection approval, because the work isn’t approved until the inspector signs it off. Put that in the payment schedule before you sign the contract.

What is a punch list in a remodel? A written list of small fixes and finishing items found during the final walkthrough. New work or changes belong in a signed change order, not on the punch list.

Do I need lien releases if I already paid my contractor? It’s wise to get them. CSLB notes that paying your contractor doesn’t guarantee subcontractors and suppliers were paid, and they may have lien rights.

What is the difference between a conditional and an unconditional lien release? A conditional release takes effect only once the person is actually paid. An unconditional release says payment has been received. Get the conditional one before you pay and the unconditional one after the payment clears.

How long do I have to record a Notice of Completion in California? Within 15 days after the date of completion, under Civil Code section 8182.

Want a finish line you can see from day one?

A smooth closeout starts with the contract: a payment schedule tied to real milestones, written change orders, and a clear picture of what “done” means.

De Sisto Construction, Inc. is a California licensed general contractor (CSLB #803545) serving greater Los Angeles and Orange County since 2001. We guide permitting, inspections, and code-compliance coordination, and we put together step-by-step outlines and line-item project costing, so you know what each stage includes before work starts. Take a look at our residential remodeling services, including kitchens, bathrooms, room additions, and ADUs.

Give us a call at 562-425-1050 or email us at info@desistogc.com (dcidirect.net)

Leave a Reply

Your email address will not be published. Required fields are marked *